Over the past couple of weeks we have been working on an ongoing project for an existing customer in which we are replacing the dated conveyers and even more dated electrical control system.

We are nearly finished now with all cable containment required for the first phase of this project in readiness for the cabling to be completed before the end of this month. We are very busy in the office building also preparing the installation drawings and cable schedules for the install.

Also , we are 90% complete of the electrical control drawings and new Siemens S7 -1500 PLC program using Tia portal which we have designed and built from scratch for our customer.

With the completion date upcoming in the mid part of December we are all working hard to make sure to achieve completion on time.